Hi Gurus,
We are in SRM Extended classic scenario with 5.0 version.
Here in SRM we have Procurement contact with process type Global Outline Agreement (GCTR).
Currently we are facing problem while amending the condition type in the contact line item. When we change the condition type for particular line item then getting error message "Leave Unit of Measure for calculation type A empty. (item 10).
On the line item the condition could look like this
Condition                    Price                 Start Date       End Date      
Price(Contract/Bid)    100 EUR            2010-02-22    2010-12-31
gross surcharge %   5,5 %                2010-02-22    2010-03-31
gross surcharge %   6,5%                 2010-04-01    2010-06-30
gross surcharge %   8,5 %                2010-07-01    2010-12-31
when we try to add additional conditon like "gross surcharge %" then we got this error message
Leave unit of measure for calculation type A empty
if I delete all condition "Gross Surcharge%" then the error disapear and then I can try again, sometime we could create those condition without problems but offen we have this error.
Can any one help me to get rid of this error message.
Thanks In Advance,
Jakob Bang

Answers

initially you could do multiple periods but when you change the condition it is not allowing you.
can you make inactivate that andd new line item and add same item with new condition
(SRM might have limitations)
I tried this works for me
MM 123 -
FIRST :-
price contract bid - 43.99 USD 2010.09.02  to 2010.09.02
Discount (Absolute) - 3 %  2010.09.02  to 2010.09.02
Discount (Absolute) - 5 % 2010.09.03  to 2010.09.03
same GOA edited change version created
price contract bid - 43.99 USD 2010.09.02  to 2010.09.02
Discount (Absolute) - 4 %  2010.09.02  to 2010.09.02
Discount (Absolute) - 5 % 2010.09.03  to 2010.09.03
no erorr for me and GOA released too and reached backend too.
Muthu

Read other 4 answers

Tags:

Related Articles

  • Leave unit of measure for calculation type A emptyNovember 30

    Hi Gurus, We are in SRM Extended classic scenario with 5.0 version. Here in SRM we have Procurement contact with process type Global Outline Agreement (GCTR). Currently we are facing problem while amending the condition type in the contact line item.

  • Unit of measure for calculation type C must be completedOctober 11

    Hi All When releasing some contracts in SRM , we are getting the error message as above. The error message doesn't specify any particular part and the contract has more than 3000 parts. There are no conditions at header or item level. There is no Tar

  • Re: Unit of measure for Activity TypeNovember 30

    Dear All, I am using 4 activity types i.e. POWER/MACHINE/STEAM/LABOUR. MACHINE & LABOUR are calculated using same formula: like Machine=machine*(SAP_09/SAP_08) Labour=Labour*(SAP_09/SAP_08) & for POWER & STEAM  I am using: Power=(Power(machine

  • Cost is showing wrongly in CK11N due to Unit of Measurment (UOM)November 30

    Dear Experts, Cost is showing wrongly in CK11N Std cost estimates. I maintained 95 INR in Material Master per KG, but 9.5 INR Per KG in CK11N. How to maintain Unit of measurement settings correctly. Regards, KBR.Hello Karru, I recommend these notes:

  • Unit of Measure Calculation in QueryOctober 11

    Hi, I have a few calculated keyfigures in my query for example: whats happening: KEY 1= Standard Price * Qty A = Output in (LBS) Qty unit of measure What I want is: KEY 1= Standard Price * Qty A = Output in $ How can i fix that on the query level so

  • Getting Condition Unit using Calculation TypeNovember 30

    Hi all, I got the calculation type from the table T685A with the Application value 'V' and Condition Type 'ZTUP' . The Calculation Type is 'C' which means Quantity. Can anyone please share for getting the Condition Unit (For Eg:  'EA' )  based on the

  • Calculation type  S-Number  of  shipping  unitsNovember 30

    Hello , created  new  condition  with  calculation  type  S-Numer  of  shipping  units  but  the condition  record  in  sales  order  is  found  but  never  set.....Checked  everything  and  my  settings  are  fine. What  can  be  the  problem? BR LH

  • Regarding calculation of uom(unit of measurment)November 30

    i want to display uom(unit of measure) field in dis format: - UOM IS KG -> SO QTY TO  -> (SALES ODER QTY * 1000) G -> (SALES ODR QTY / 1000) I making d report of sales order and i have to display it according to it...plzzz help me its urgent...ca

  • Maintain differ type of Unit of measurment for same materialNovember 30

    Hi Expert I procured (internal /external)   one material in Kg, but I want maintain different unit of measurement (like M). & sale is different unit of measurement (like m2).it  is possible ? If Possible kindly explain the steps Advance thanks for al

  • Pricing Procedure for diffrent unit of measure for diffrent productOctober 11

    1) Existing Pricing procedure --> Condition type based on Quantity 2) Existing Product --> Sales Unit & Base Unit of Measurement is in NOS ( Numbers ) 3) New Product ( Belt ) ---> Pricing of product based on weight ex :--> Rubber Belt --&g

Copyright (C) 2019 wisumpire.com, All Rights Reserved. webmaster#wisumpire.com 14 q. 0.542 s.