We have an issue with the Budget Commitment Report S_ALR_8701355 as explained below.
Org Structure:
A* Projects are separate small Projects to track Capital and Operating Expenses
But all the Capital Purchases are done only through C* WBS. And accordingly Capex budget is maintained only for C* WBS. So AWBS has been linked to 3 CWBS ( SW, HW & Dev SW)  in one of the user field of C*WBS.
Shopping Cart will be raised using CWBS in SRM. But once PR has been created it replaces the account assignment field with AWBS. And later even the Asset posting happens only with A*WBS
Issue:
While using Budget Commitment Report - S_ALR_87013558, CWBS is giving Budget and A WBS is giving Actual cost. This Actual Cost pertains to 3 C* WBS Elements (SW, HW & Dev SW). So now Business requires to merge the cost of A* WBS with respective C*WBS Element.
We are able ascertain the cost of AWBS but not able find a logic to distribute this cost across respective C WBS.
Current Logic of the Program:
Any document posted using WBS Element will update table RSPCO with just Amount, Period & Value Type (Actual/ Budget / Plan) . So Budget Commitment Report S_ALR_87013558 will fetch the details from this table alone.
Could any of you please let us know how to deal with this problem without altering the existing Org structure .

Answers

Hi Rajesh,
I think the report is showing correctly as per the logic. But please elobrate us why the PR created with account assignment C* WBSE is replacing by A* WBSE.
If the account assignment in PR and PO is replacing by A* WBSE then obviously actual cost will book against A* WBSE and report S_ALR_8701355 will display the same.
you can post cost from AWBSE to C WBSE uisng KB15N.
Regards,
Nag.

Read other 2 answers

Tags:

Related Articles

  • Budget Commitment Report - S_ALR_87013558October 11

    We have an issue with the Budget Commitment Report S_ALR_8701355 as explained below. Org Structure: A* Projects are separate small Projects to track Capital and Operating Expenses But all the Capital Purchases are done only through C* WBS. And accord

  • Budget/Actual/Commitment report-S_ALR_87013558October 11

    Hello Experts,                       Is it possible to get the get this report (S_ALR_87013558) on day basis? I mean to say if i want to see the balances between two particular dates WBS/Project wise, so can i get the same? Please suggest.. Thanks An

  • Please help to find table for report S_ALR_87013558 (budget commitment)October 11

    Dear SAP Guru, How can i find the table that store the value for report S_ALR_87013558 ? Many thanks in advance. NiesTABLES: RPSCO_X, COIX, COIX_DATA40, RKB1X, RKB1F, RKB1D. PROJ, PRPS_R, ACT01, AUFK, VBAK, TCNDB, VSKOPF, IMTP, IMPR, TCNDBT.Read othe

  • Budget is not getting displayed in Report S_ALR_87013558October 11

    Hi Friends, For project the budget is not getting displayed in Report S_ALR_87013558 though the budget is planned by TCode: CJ30 and released also by TCode: CJ32 Is there any setting in customising in information systems to display in the report. Ple

  • Reaminder value from standard report S_ALR_87013558 - Budget/Actual/CommitmOctober 11

    Dear Gurus, Can you explain me the source of value which is shown as 000.2009 Remainder 2009 ( I seams that 000 stands for period) in the report S_ALR_87013558 - Budget/Actual/Commitmt/Rem.Plan/Assg Regards Project Team1hi in PS all the Cost reports

  • Default setting for Budget Report S_ALR_87013558October 11

    Dear All, In Budget Report S_ALR_87013558, when it is executed every time when we enter, 2 number formats are displayed, one in Lakhs (Factor 1,00,000) and one in units (Factor 1). When I change it to Factor 1 through "Number format", then it co

  • Mismatch of Assigned Budget in CJ33 & Report S_ALR_87013558October 11

    Hi, I would like to inform there is an issue in mismatch of assigned budget value in CJ33 wrt hierarchical report(S_ALR_87013558). Request you to suggest to fix the issue. Thank you for your coopearation. Regards, RanjanRanjan, removing a column in a

  • REPORT S_ALR_87013558 - budget in Controlling area currency not correctOctober 11

    Hi , these are the budget column settings : Key figure          Overall in CAC Version     0     Plan/Act - Version Value Type     41     Budget Object ind.     P     Project item Debit type     1     Costs and credit-side payments My case is the fol

  • Budget not appearing in Report S_ALR_87013558October 11

    Hi Friends, For project the budget is not getting displayed in Report S_ALR_87013558 though the budget is planned by TCode: CJ30 and released also by TCode: CJ32 Is there any setting in customising in information systems to display in the report. I t

  • How to avoid wrong budget values on S_ALR_87013558 report?October 11

    Hi experts. In the budget drilldown report S-ALR_87013558, the budget column is displaying values that do not match budget profile exchance rates, as well as other rates defined in "currency" button. Other column show expected values according t

Copyright (C) 2019 wisumpire.com, All Rights Reserved. webmaster#wisumpire.com 14 q. 0.499 s.